Corbeau Hydroelectric Station

The Corbeau Hydroelectric Station was completed in December 2015 by Decontie Construction Inc.

Project objectives/ description:

Decontie Construction Inc. was awarded a contract to demolish a former run of the river Hydro Québec hydroelectric power station and return the site to its natural state.  The Corbeau Station, situated on the Gatineau River just outside Maniwaki, Québec, was built in 1905 by a group a  business people from Maniwaki, was in use until the early 1980’s.The Corbeau site was also at  the edge of the Anishinabe (Algonquin)  community of Kitigan Zibi and the only access road to  the site crosses through Kitgan Zibi territory.

The Corbeau Hydroelectric Station decommissioning project saw Decontie lead a team of three  contracting firms to dismantle an abandoned Hydro Québec generating station in a challenging environment. This project, a  first outside reserve boundaries for Decontie, was valued at $4.5 million. Decontie retained the services of two non-First Nations companies to conduct specialty services such as environmental remediation of hazardous substances, civil engineering for the  construction of cofferdams, and  demolition of the building itself.

 

The team:

Decontie engaged  the  support  of  an  experienced  company  to  help  guide  and  manage  the  project.    Decontie  was  able  to  leverage Milestone  Environmental  Contracting  Inc.’s  experience  as  a  general  contractor  and  project  manager  to  successfully  respond  to  the  Hydro  Québec  tender  call.  The  two companies  worked together seamlessly to execute and  manage the project. The team also reached out to a trusted subcontractor, Demolition Plus, to apply their expertise  relating to heavy civil earthworks and demolition services.

In accordance with the AMWD established for the project, the Corbeau project  created  and  employed  over  30  new  jobs  for  Anishinabeg. The  general  contractor  project  team  directly  involved  Anishinabeg  labourers,  heavy  equipment  operators,  skilled  tradesmen, administrators and site supervisory staff for the duration of the project.  Specifically, Anishinabe workers were responsible  for  site  access  and  security,  road  construction  and  maintenance,  operation  of  heavy  equipment,  wood  clearing  and         grubbing,   shovel and timber jack  operators, trucks and drivers, site foremen and supervisors.   Services that involved the    community of Kitigan Zibi that contributed to the overall success of the project included police  surveillance, food catering,  printing and communication products, local CKWE radio station, and KZA public works.

 

Project outcomes:

The Corbeau  project  proved  to  be  a  tremendous  success  for  all  parties  involved. The success of the project is a  true  testament  to  the  collaborative  approach  embraced  by  all  stakeholders,  right  from  Hydro  Québec,  KZA,  CCQ,  local  labour  and    construction  workforce,  and  specialized  subcontractors  that  were    working  towards  one  common  goal.   In  addition  to  the  project  objectives being  realized,  the Corbeau decommissioning also created  numerous positive outcomes for the local community and workforce.   As mentioned above,  over  30 Anishinabeg workers were involved at  all  levels  of  the  project,  and  gained  valuable  transferable  skills  and      meaningful  employment  experience  that  will  support  future employment  opportunities  both  locally  and  beyond  the  borders  of  Kitigan Zibi.

In  terms  of  measuring  the  success  of  the  project  the  following  key  metrics  demonstrate  the  significance  of  the  positive  outcomes generated by the project:

  • In-water works (removal of upstream/downstream cofferdams and construcƟon of fish spawning beds) completed 12  days ahead of mandated contract deadline;
  • Site restoration, slope stabilization and seeding completed in December 2015, a full 5  to 6 months ahead of anticipated  construction schedule;
  • A total of 30 Anishinabeg workers employed on the project;
  • Specialized construction sector training was provided;
  • A KZ shovel operator was apprenticed by a KZ shovel operator journeyman;
  • A total of 812 hours of independent KZ truckers (dump trucks) were hired by the project
  • A total of 1,496 truckloads (~ 25,500 metric tons)  of material (sand, gravel, 50-150 mm and 400 mm + cofferdam rock)
  • was hauled onto the site by KZ truckers;
  • A total of 1,930 truckloads (~28,000 metric tons) of material (cofferdam rock, crushed concrete, rubble etc.) was hauled  off-site by KZ truckers;
  • A  total  of  1,558  truckloads  of  clean  fill  material  was  accepted  by  a  neighbouring  landowner  for  beneficial  reuse  to      improve grading and access on their property.

 

With the support of the KZA, Decontie  and his Contracting Team,  was proud to act as the Algonquin general contractor for  this  challenging and high-profile project. This project and  the establishment of AMWD provided a great opportunity  to  further  the  development of a workforce of First Nations trades workers and for some, gave  them the on-the-job training opportunities they  need  to  complete  their  certifications.
Overall,  the  outcomes  of  the  project  were  achieved,  the  community  has  gained  and benefited  from  social,  economic  and  environmental  impacts  from  the  project,    and  the  construction  industry  has  acquired  trained and certified workers in their workforce.

Decontie  is  grateful  that  Hydro  Québec  believed  firmly  in  the  importance  of  consulting  and  retaining  a  contractor  from  the      Algonquin Nation.  This project gave Anishinabeg  workers the opportunity to practice their trades and complete their on-the-job  training requirements. Decontie will use this project as a spring board to further recruit, hire and train an Algonquin-Anishinabeg  construction workforce for their integration in the construction industry.

We believe passionately in the importance of giving back to communities, and we wish to work with partners such as KZA,  INAC,  Hydro  Québec,  CCQ,  that  share  our  beliefs,  particularly  as  they  pertain  to  advancing  the  interests  of  Canada’s  First  Nations     people in the  construction industry.